Home › Articles › Infrastructure › Eldoret Dropped From AFCON 2027 Plans as KipKeino...

Eldoret Dropped From AFCON 2027 Plans as KipKeino Stadium Stalls at 18% Completion

Aerial view of KipKeino Stadium in Eldoret under construction, showing incomplete stands, running track and extensive scaffolding.
KipKeino Stadium in Eldoret at 18% completion, now excluded from AFCON 2027 hosting plans. | Eric Njiru/X
Kenya will host AFCON 2027 matches only in Nairobi after the Sports PS confirmed KipKeino Stadium in Eldoret cannot be finished in time, leaving the project at just 18% progress with six months to key deadlines.

Eldoret has been removed from Kenya’s hosting plans for AFCON 2027. The KipKeino Stadium, designed for 15,000 capacity, stands at only 18 percent completion despite years of construction work.

Sports Principal Secretary has briefed the National Assembly committee on Sports that the facility will not meet the required readiness timeline. As a result, Kenya will stage all its AFCON 2027 matches in Nairobi, using Talanta and Kasarani stadiums as primary venues. Nyayo and Ulinzi will serve as training grounds.

The decision highlights persistent delays in county-level sports infrastructure projects. KipKeino Stadium has been under construction since around 2018. Recent aerial images show extensive scaffolding on main stands, incomplete concrete works, exposed reinforcement bars and limited progress on spectator terraces and ancillary buildings.

The project was expected to provide a modern multi-purpose venue in the North Rift. Its slow pace now forces a more centralised hosting model for the continental tournament co-hosted with Uganda and Tanzania.

Talanta Stadium in Nairobi has been positioned as the main venue and potential CAF headquarters location. Kasarani, with its larger capacity, will complement it. This concentration reduces pressure on regional sites but raises questions about infrastructure equity and long-term legacy in other parts of the country.

Construction challenges at KipKeino mirror broader issues seen in several Kenyan public stadium projects. Delays often stem from funding gaps, procurement problems, contractor performance and shifting priorities. With only six months remaining to critical AFCON readiness deadlines, completing the remaining 82 percent appears unfeasible.

The ministry’s confirmation comes amid ongoing parliamentary scrutiny of sports infrastructure spending. Observers note that small to mid-size stadiums can become prolonged financial commitments when not delivered on schedule.

For Eldoret and the wider Rift Valley region, the exclusion means missing out on direct economic benefits from hosting international matches. Local football stakeholders and residents have expressed disappointment over the prolonged works.

Kenya’s overall AFCON 2027 preparation now focuses heavily on upgrading and certifying Nairobi facilities. While this approach ensures compliance with Confederation of African Football (CAF) standards, it limits geographic spread of the tournament’s impact.

KipKeino Stadium, named after legendary athlete Kipchoge Keino, was intended to honour athletics heritage while boosting football and other sports. Its current state—with partial stands, unfinished structures and active but slow site activity—reflects the difficulties of delivering time-sensitive flagship projects.

The development leaves questions about the stadium’s future use and maintenance once the tournament window passes. Similar facilities built or upgraded for past events have sometimes struggled with post-event utilisation.

Comments (0)

Leave a Comment

0/1000 characters

No comments yet. Be the first to share your thoughts!